City of Austin | Performance Measures

City of Austin

Performance Measures

Department Director: Adriana Castaneda -
Department Website: No Website
Department Phone:

Measure:

Percent of projects with Quality Management Division design review completed in 10 days or less
Measure Description
Timely design review ensures that CIP projects move through final design to bid and award and remain on schedule. Timely QA review ensures that Project Managers and designers can address any issues which would create risk to the project during award or construction.
Measure Type
Output

Current Data - Quarterly

2026 Target Q1 Q2 Q3 Q4 2026 Actuals
90 82 80 0 0 0

Historical Data - Last 5 Years

FY 2021 Actual FY 2022 Actual FY 2023 Actual FY 2024 Actual FY 2025 Actual FY 2025 Target FY 2026 Target
No Data No Data 73 84 88 81 90