City of Austin | Performance Measures

City of Austin

Performance Measures

Department Director: Shay Roalson - Director
Department Website: http://www.austintexas.gov/department/water
Department Phone: 512-494-9400

Measure:

Percent of CIP Project funds invested compared to planned spending via CIP Budget
Measure Description
The measure tracks actual CIP spending expended during the fiscal year as a percentage of the CIP budgeted for that year. CIP spending affects both the issuance of debt and transfers of current revenue to CIP, thus impacting rates, so it is important to try to spend CIP money as budgeted.
Measure Type
Result

Current Data - Quarterly

2026 Target Q1 Q2 Q3 Q4 2026 Actuals
85 87.2 93.54 105.84 No Data No Data

Historical Data - Last 5 Years

FY 2021 Actual FY 2022 Actual FY 2023 Actual FY 2024 Actual FY 2025 Actual FY 2025 Target FY 2026 Target
112 103.36 107.570 105.5 111.3 95 85